Example Asbestos Removal Projects in Bellflower

The seven example jobs below are set in Bellflower, Artesia and South Whittier. Each one lists what was sampled, what came out, the work days and an estimated cost.

House cleared of positive materials before demolition, with the survey in the application

Example project

Home
1950s house of about 1,100 sq ft in Bellflower
Original request
Take the house down and build a new one on the lot
Testing
A comprehensive survey of the whole building by a Cal/OSHA-certified asbestos consultant, about 18 samples from ceilings, floors, walls and the furnace closet
Found
Asbestos in the ceiling texture, the kitchen and bath flooring and the wall compound
Clear
The garage walls
Area
About 1,000 sq ft of ceiling, 280 sq ft of floor and 350 sq ft of wall
Timeline
Notice no later than 10 working days ahead, then five working days before the wrecking crew
Cost
$16,500

Scope of work

Removal of every positive material in the survey, the district notice, rooms sealed in turn, wet removal into labeled bags and the haul with its paperwork. The survey, the clearance air test, the demolition itself, the permits and the new house are separate.

Project overview

In this example, an owner in Bellflower is replacing a 1950s house. The city requires each demolition application to come with a comprehensive asbestos survey and the Rule 1403 paperwork, so both are in hand before the application goes in.

The survey finds asbestos in four materials. The abatement crew removes them after the district notice is filed, and the wrecking crew starts once the air results are in.

The goal

The goal is a demolition application with its paperwork complete, and a house with every positive material removed before the wrecking crew starts.

Process

  1. First visit A Cal/OSHA-certified asbestos consultant samples every room, the garage and the furnace closet.
  2. Before work The contractor files the district notice online, and the owner adds the survey and the notice paperwork to the demolition application.
  3. Days one to five Room by room the ceilings, floors and wall compound come out wet and leave in sealed bags.
  4. Last An independent consultant checks the air, and the wrecking crew starts.

Planning right

  • Order the survey before you fill in the application.
  • Keep the survey and the notice paperwork in one folder.
  • Ask the wrecking crew to wait for the air results.
  • Keep the driveway clear for the work truck.

Get a free quoteMore about renovation and demolition abatement

Ceiling texture removed from a rear addition before it is demolished, with the manifest in the permit file

Example project

Home
1960s house in Bellflower with a rear family room and bath added later
Original request
Take the rear addition down to make room for a larger yard
Testing
A Cal/OSHA-certified asbestos consultant samples the ceiling texture in the family room, the bath and the hall to the addition
Found
Asbestos in the ceiling texture of all three
Clear
The addition walls
Area
About 480 sq ft of ceiling
Timeline
Notice no later than 10 working days ahead, then two working days before the wrecking crew
Cost
$4,600

Scope of work

Samples, the district notice, the addition sealed from the house with air filters running, the texture soaked and scraped into bags, a HEPA clean and the haul with its manifest. The clearance air test, the demolition and the permits are separate.

Project overview

In this example, a Bellflower owner is demolishing a rear addition. Demolition always needs the district notice, and the city asks for the hazardous materials manifest when asbestos was removed.

The ceiling texture tests positive, so the abatement crew takes it down before the wrecking crew arrives. The hauler’s copy of the manifest goes into the permit file.

The goal

The goal is an addition free of positive ceiling texture, with the disposal paperwork in the permit file.

Process

  1. First visit A Cal/OSHA-certified asbestos consultant samples the ceilings of the addition and the hall.
  2. Before work The abatement contractor files the district notice online.
  3. Days one and two The addition is sealed off from the house, and the texture is soaked and scraped into bags.
  4. Last An independent consultant tests the air, the manifest copy is filed and the wrecking crew starts.

Planning right

  • Ask the contractor for the manifest copy by name.
  • Keep the lab report and the manifest together.
  • Move belongings out of the hall to the addition.

Get a free quoteMore about popcorn ceiling removal

Kitchen flooring and wall compound removed before a county-permitted remodel

Example project

Home
1950s ranch house in South Whittier, an unincorporated community, with sheet flooring and textured wall compound in the kitchen
Original request
Put in new cabinets, a new floor and an opening to the family room under an alteration permit
Testing
A Cal/OSHA-certified asbestos consultant samples the flooring and its backing, and the compound on the wall
Found
Asbestos in the flooring backing and the wall compound
Clear
The ceiling paint and plaster
Area
About 180 sq ft of floor and 70 sq ft of wall
Timeline
If the address is in the district’s area, notice no later than 10 working days ahead, then three working days
Cost
$3,800

Scope of work

Samples of each material, the kitchen sealed with air filters running, the flooring and the compound removed wet, bagging and the haul. The clearance air test, the county permit and the new cabinets and floor are separate.

Project overview

In this example, a South Whittier owner is remodeling the kitchen of a 1950s ranch house. The community is unincorporated, so the permit comes from Los Angeles County Public Works Building and Safety, which asks for a notification form on alteration permits where asbestos is involved.

The flooring backing and the wall compound test positive. If the address is inside the district’s area, the contractor files the district notice online, and the crew clears both materials before the cabinets arrive.

The goal

The goal is a kitchen with the positive floor and wall material gone before the remodel work begins.

Process

  1. First visit A Cal/OSHA-certified asbestos consultant samples the kitchen floor and walls.
  2. Before work The owner completes the county notification form with the permit, and the contractor files the district notice online if it applies.
  3. Days one to three The kitchen is sealed, the flooring is lifted and the wall compound is removed wet.
  4. Last An independent consultant tests the air before the cabinet crew starts.

Planning right

  • Ask the county counter which asbestos form goes with your permit.
  • Keep the lab report with the permit papers.
  • Set up a small cooking spot elsewhere.
  • Schedule the cabinet delivery after the air test.

Get a free quoteMore about renovation and demolition abatement

Hall bathroom floor and wall tile sampled before a remodel

Example project

Home
1960s house in Artesia with a hall bathroom tiled on the floor and around the tub
Original request
Replace the floor tile and the tub wall tile
Testing
A Cal/OSHA-certified asbestos consultant takes six samples from the floor tile, its mastic, the wall tile adhesive and the wall compound
Found
Asbestos in the wall tile adhesive
Clear
The floor tile, its mastic and the wall compound
Timeline
Samples, then lab results, then a short report
Estimated testing cost
$600

Scope of work

A visit by the consultant, six samples, a lab result for each and a short report that names every sample and its spot. Removing the adhesive is priced on its own.

Project overview

In this example, an Artesia owner is replacing the tile in a hall bathroom of a 1960s house. The floor and the wall are tiled with different materials, so each layer is sampled.

Only the adhesive behind the wall tile tests positive. The report says where each sample was taken, and the abatement crew is booked for the tub wall before the tile setter.

The goal

The goal is a written record of each layer, so the new tile goes in with the positive adhesive dealt with first.

Process

  1. First visit A Cal/OSHA-certified asbestos consultant takes six small samples from the floor and the tub wall.
  2. Results The lab reports each sample, with the wall adhesive positive and the rest clear.
  3. Next The abatement crew is booked for the tub wall.
  4. Then The tile setter starts on the floor and the wall after that.

Planning right

  • Please do not chip at the tile to look behind it.
  • Ask the consultant to mark each sample spot on a sketch.
  • Keep the report with the remodel papers.

Get a free quoteMore about asbestos testing and surveys

Textured wall compound removed from a triplex unit between tenants

Example project

Home
Front unit of a 1950s triplex in Bellflower, with a textured living room and hall
Original request
The owner is putting in new wiring and paint between tenants
Testing
A Cal/OSHA-certified asbestos consultant samples the wall texture and the joint compound in the living room, the hall and a bedroom
Found
Asbestos in the wall texture and the joint compound of the living room and hall
Clear
The bedroom walls
Area
About 380 sq ft of wall
Timeline
Notice no later than 10 working days ahead, then three working days
Cost
$3,600

Scope of work

Samples, the district notice, the unit sealed with air filters running, the wall texture and compound removed wet, bagging and the haul. The clearance air test, the wiring, new drywall and paint are separate.

Project overview

In this example, the owner of a 1950s triplex is rewiring the front unit between tenants. A triplex is not a residential single-unit dwelling, so the small-job survey exemption for single-unit homes does not apply to it.

The living room and hall walls test positive and the bedroom walls are clear. The abatement crew strips the two spaces while the unit is empty, and the electrician works in a clean unit.

The goal

The goal is a unit with the positive wall material gone, so the rewiring and paint go on a clean surface.

Process

  1. First visit A Cal/OSHA-certified asbestos consultant samples the walls room by room.
  2. Before work The abatement contractor files the district notice online, and the unit stays empty.
  3. Days one to three The unit is sealed and the wall texture and compound come off wet.
  4. Last An independent consultant tests the air, then the electrician starts.

Planning right

  • Hold the next lease until the air results.
  • Let the neighbors know the work days.
  • Keep the report with the building records.

Get a free quoteMore about drywall, joint compound and plaster removal

Closet ceiling texture and duct tape removed at a new attic hatch

Example project

Home
1960s house in Bellflower with a furnace in the attic and no easy way up
Original request
Cut a new attic hatch in the hall closet ceiling so the furnace can be serviced
Testing
A Cal/OSHA-certified asbestos consultant samples the closet ceiling texture, the duct wrap at the first run and the tape at two joints
Found
Asbestos in the closet ceiling texture and the joint tape
Clear
The duct wrap
Area
About 10 sq ft of ceiling and two duct joints
Timeline
Less than 100 square feet of asbestos-containing material removed, so no district notice, then one working day
Cost
$1,600

Scope of work

Samples, plastic around the closet and hall, the texture and the joint tape removed wet and bagged, a cleanup and the haul. The clearance air test, the hatch and the carpentry are separate.

Project overview

In this example, a Bellflower owner wants a proper hatch to the attic furnace. A hatch in the closet ceiling means cutting through texture, and the first duct joints sit right above it.

The ceiling texture and the joint tape test positive and the duct wrap is clear. The abatement crew removes both in one visit, and the carpenter cuts the hatch afterwards.

The goal

The goal is a hatch opening and duct joints with no positive material left to disturb.

Process

  1. First visit A Cal/OSHA-certified asbestos consultant samples the closet ceiling and the nearest duct joints.
  2. Results The texture and the tape are positive, and the wrap is clear.
  3. Work day The closet and hall are sealed, and the texture and tape are removed wet and bagged.
  4. Then The carpenter frames the new hatch.

Planning right

  • Empty the hall closet.
  • Please do not cut the hatch before the survey is done.
  • Keep the report with the furnace service records.

Get a free quoteMore about HVAC duct and pipe insulation removal

Sheet vinyl and mastic removed from a rental kitchen between tenants

Example project

Home
1960s rented house in Bellflower with sheet vinyl in the kitchen
Original request
The landlord is replacing the floor and the counters while the house is empty
Testing
A Cal/OSHA-certified asbestos consultant samples the vinyl, its backing and the mastic at three spots
Found
Asbestos in the mastic
Clear
The vinyl and its backing
Area
About 220 sq ft of kitchen floor
Timeline
Notice no later than 10 working days ahead, then two working days
Cost
$3,000

Scope of work

Samples, the district notice, the kitchen sealed with air filters running, the vinyl lifted and the mastic removed wet to the subfloor, bagging and the haul. The clearance air test and the new floor are separate.

Project overview

In this example, a landlord in Bellflower is renewing the kitchen floor of a rented 1960s house between tenants. The house is empty, so the crew can work without anyone living there.

The vinyl and its backing are clear, but the mastic beneath tests positive. The abatement crew removes all three layers in one visit, and the flooring installer starts on bare subfloor.

The goal

The goal is a bare kitchen subfloor, so the new floor goes down with no old mastic below it.

Process

  1. First visit A Cal/OSHA-certified asbestos consultant samples each layer where the vinyl has lifted.
  2. Before work The abatement contractor files the district notice online.
  3. Day one The kitchen is sealed, and the vinyl is lifted and bagged.
  4. Day two The mastic comes off wet, the subfloor is cleaned and an independent consultant tests the air.

Planning right

  • Book the work between tenants.
  • Ask the consultant to list each layer in the report.
  • Hold the counter delivery until after the air test.

Get a free quoteMore about floor tile and mastic removal

Request a free asbestos removal quote

We recommend calling, but do feel free to contact us using this form. We'll get back to you with a free, personalized quote or additional questions as soon as possible. We're here to help.

Call (562) 263-3544

Call (562) 263-3544