House cleared of positive materials before demolition, with the survey in the application
Example project
- Home
- 1950s house of about 1,100 sq ft in Bellflower
- Original request
- Take the house down and build a new one on the lot
- Testing
- A comprehensive survey of the whole building by a Cal/OSHA-certified asbestos consultant, about 18 samples from ceilings, floors, walls and the furnace closet
- Found
- Asbestos in the ceiling texture, the kitchen and bath flooring and the wall compound
- Clear
- The garage walls
- Area
- About 1,000 sq ft of ceiling, 280 sq ft of floor and 350 sq ft of wall
- Timeline
- Notice no later than 10 working days ahead, then five working days before the wrecking crew
- Cost
- $16,500
Scope of work
Removal of every positive material in the survey, the district notice, rooms sealed in turn, wet removal into labeled bags and the haul with its paperwork. The survey, the clearance air test, the demolition itself, the permits and the new house are separate.
Project overview
In this example, an owner in Bellflower is replacing a 1950s house. The city requires each demolition application to come with a comprehensive asbestos survey and the Rule 1403 paperwork, so both are in hand before the application goes in.
The survey finds asbestos in four materials. The abatement crew removes them after the district notice is filed, and the wrecking crew starts once the air results are in.
The goal
The goal is a demolition application with its paperwork complete, and a house with every positive material removed before the wrecking crew starts.
Process
- First visit A Cal/OSHA-certified asbestos consultant samples every room, the garage and the furnace closet.
- Before work The contractor files the district notice online, and the owner adds the survey and the notice paperwork to the demolition application.
- Days one to five Room by room the ceilings, floors and wall compound come out wet and leave in sealed bags.
- Last An independent consultant checks the air, and the wrecking crew starts.
Planning right
- Order the survey before you fill in the application.
- Keep the survey and the notice paperwork in one folder.
- Ask the wrecking crew to wait for the air results.
- Keep the driveway clear for the work truck.